Emergency response and stabilization following a devastating fire that compromised the entire building
Coordination with the owner, Department of Buildings (DOB), FDNY, and insurance carrier to secure the site and safely dismantle the damaged structure
Selective demolition with a focus on preserving as much of the existing building as possible
Development and execution of a full reconstruction plan in coordination with the owner
Conversion of a former one-story building into a 9,000 SF high-bay warehouse with 3,500 SF of second-floor office space
Installation of new footings, structural steel, and floor slabs within the existing building envelope
Construction of a new passenger elevator serving the second-floor office area
Complete replacement of all plumbing, electrical, and mechanical systems
Installation of a new building envelope including brick veneer with cast stone accents, windows, overhead doors, and a new roof